Water, water everywhere!

Our utility contractor has completed the installation of water supply pipes from the city water main up to our building!
  Spacemaker’s sub-contractors will now start connecting the water mains to the building’s plumbing system and fire suppression sprinkler system.  Multiple inspections will be required in the process.
By the end of February, several concrete slabs should be poured: the kitchen extension, the hallway connecting the sanctuary with the social hall wing, the floor of the new entrance vestibule, and a slab at the West end of the sanctuary to support heating and air-conditioning systems.
Painting of roof dormers is being done whenever the weather permits. Construction of ramps from the four emergency exit doors in the children’s wing has just begun.  Installation of heating and cooling systems is underway.
You can see photos of progress on our new building after Sunday services in the social hall.